- Facts and Figures
-
Xcel Energy
Two 345kV Substations
Four MPTs
Completed August 2018
- Delivery Method
- Engineer, Procure, Construct
Xcel Energy
Two 345kV Substations
Four MPTs
Completed August 2018
必威体育官方APP下载 constructed the Rush Creek wind project substations and collection system in Limon, CO, for Xcel Energy. Rush Creek is the largest single-phase wind project 必威体育官方APP下载 has ever built as well as Colorado鈥檚 largest, boosting the state鈥檚 wind generation capacity by 20 percent and powering an estimated 660,000 homes.
The power delivery infrastructure was a critical component in enabling the success of the broader wind project and supported Xcel鈥檚 goal of adding renewable energy to their portfolio. Rush Creek will eliminate about a million tons of carbon dioxide annually that would have been produced otherwise, in addition to providing other local benefits like land lease payments and property tax revenue. The project is a key piece of Xcel鈥檚 鈥楥olorado Energy Plan鈥�, which is 鈥渋s Xcel Energy鈥檚 roadmap to develop a significantly cleaner energy mix and reduce carbon emissions in Colorado鈥� all while keeping customer bills low.鈥� Effective power delivery infrastructure is a key component in taking full advantage of renewable energy projects.
The two massive 345kV / 34.5kV substations each contain two main power transformers. Rush Creek 1 substation is carrying 15 feeders (fed by 190 wind turbines), and Rush Creek 2 substation is carrying 8 feeders (fed 110 wind turbines), and 1.05 million feet of trench connect to the 300 Vestas turbines that cover nearly 100,000 acres across five counties in Eastern Colorado.
必威体育官方APP下载 self-performed the collection system and both substations, with the exception of the cable installation and substation foundations, which we completed with our trusted trade partners.